Share Hwy 63 - Spring Valley Reconstruction on FacebookShare Hwy 63 - Spring Valley Reconstruction on TwitterShare Hwy 63 - Spring Valley Reconstruction on LinkedinEmail Hwy 63 - Spring Valley Reconstruction link
View full-sized imageWe are planning to reconstruct portions of Hwy 16/Hwy 63 and make ADA improvements. Construction is anticipated to occur in 2030.
Improvements include:
Hwy 16/Hwy 63: Tracy Rd. to Griswold St.(Orange section)
Please note, at this time, this section will not receive changes to the roadway
Public meeting
Join us Wednesday, May 22nd to learn review the first design concepts and provide your feedback. The meeting is drop-in style, so no formal presentation is planned. People may come and go at their convenience.
Please note, at this time, this section will not receive changes to the roadway
Public meeting
Join us Wednesday, May 22nd to learn review the first design concepts and provide your feedback. The meeting is drop-in style, so no formal presentation is planned. People may come and go at their convenience.
MnDOT is planning to reconstruct Hwy 16/63 and make Americans with Disabilities Act (ADA) improvements. In 2030, the project will:
Remove the entire road from Tracy Rd. to Griswold St. and replace it with new materials
The City of Spring Valley will replace local sewer and water utilities
Install new and upgrade ADA facilities from the Hwy 16/63 intersection to Sample Rd.
During the summer 2023, we heard from community members about their experiences with and priorities for the road. We received suggestions regarding improvements for roadway intersections and pedestrian facilities.
Based on this feedback, we’ve developed concept improvements. As MnDOT prepares to design of the roadway, we are again seeking input to help us prioritize this work.
People are welcome to participate by reviewing the information that follows and provide feedback through the survey. They can also join us Wednesday, May 22 at a public meeting. The information is the same.
This survey will close June 5, 2024.
To the extent information submitted in connection with this engagement opportunity identifies an individual or business, the information may be protected from disclosure under the Minnesota Government Data Practices Act (MGDPA). Any identifying information you provide will not be associated with your individual responses. However, any identifying information will be accessible to MnDOT employees, agents, consultants and contractors with a business need to access the information, and others as required by court order or as authorized by federal or state law. Minor individuals who have provided information on this site have the right to request that parental access to the private data on the minor, be denied. You are not obligated to respond to this engagement opportunity, and there are no consequences if you do not respond. However, if you do not respond, MnDOT may not fully understand who is providing input on the transportation projects, plans and programs for which it is seeking public input.
Share Design review, May 2024 on FacebookShare Design review, May 2024 on TwitterShare Design review, May 2024 on LinkedinEmail Design review, May 2024 link
This comment map closed Aug. 30, 2023. Thank you to everyone who participated. A summary of the feedback provided by the community is available for review.
If you missed the deadline and would like to submit a comment, please reach out to Cindy Morgan at Cindy.Morgan@state.mn.us or 507-951-6593.
We are planning to reconstruct portions of Hwy 16/Hwy 63 and make ADA improvements.
From Tracy Rd to Griswold St., we plan to remove the road surface and replace it with new materials. We also plan to replace the sidewalks and make other improvements.
We do not plan to make any changes to the road from the Hwy 16 intersection to Co. Rd. 12. However, we plan to make pedestrian improvements, sidewalk repairs and improve drainage.
Please take this short survey about Hwy 63 from Tracy Rd. to Griswold St. Your feedback is important and will help shape the future of this roadway.
This survey will close at midnight Aug. 30, 2023.
To the extent information submitted in connection with this engagement opportunity identifies an individual or business, the information may be protected from disclosure under the Minnesota Government Data Practices Act (MGDPA). Any identifying information you provide will not be associated with your individual responses. However, any identifying information will be accessible to MnDOT employees, agents, consultants and contractors with a business need to access the information, and others as required by court order or as authorized by federal or state law. Minor individuals who have provided information on this site have the right to request that parental access to the private data on the minor, be denied. You are not obligated to respond to this engagement opportunity, and there are no consequences if you do not respond. However, if you do not respond, MnDOT may not fully understand who is providing input on the transportation projects, plans and programs for which it is seeking public input.
Share Community Survey, July 2023 on FacebookShare Community Survey, July 2023 on TwitterShare Community Survey, July 2023 on LinkedinEmail Community Survey, July 2023 link
Page last updated: 08 May 2024, 03:02 PM
Sign up for email updates
Project Schedule
Phase 1: Data collection
Hwy 63 - Spring Valley Reconstruction has finished this stage
April-July 2023
Gather background data
Introduce the study and gather feedback on the issues in the corridor
Phase 2: Develop designs
Hwy 63 - Spring Valley Reconstruction has finished this stage
July-December 2023
Project team will develop design concepts
Feedback from Phase 1 will help the team narrow in on options
The community and other stakeholders will provide additional feedback, which the team will use to refine the concept(s)
Phase 3: Recommended concept selection
Hwy 63 - Spring Valley Reconstruction has finished this stage
January-April 2024
Project team will determine the final layout and which features/changes to include
Phase 4: Final report
Hwy 63 - Spring Valley Reconstruction is currently at this stage
May-June 2024
Project team will present the final design to the community and stakeholders