Hwy 14 and Co. Rd. 9 — J-turn
Please go to the construction website to see the most up-to-date information about the schedule, detour details, etc. This website was used during the public engagement and design phase of the Hwy 14 project. That phase is complete, so now information about the project is on the construction website.
About the project
We will make improvements on Hwy 14 from east of Hwy 56 in Dodge Center to west of Co. Rd. 5 / 2nd Ave. in Byron. Construction will take place spring 2024 and end late summer 2024. The project includes the following improvements:
- Construct a J-turn (also known as a Reduced Conflict Intersection) at Hwy 14 and Co. Rd. 9
- Install a high-tension cable median barrier between Dodge Center and Kasson
- Resurface pavement between Kasson and Byron
- Improve and repair drainage
- Rehabilitate the eastbound and westbound Hwy 14 bridges over Hwy 57. The work includes new end posts, approach panels and expansion joints
- Upgrade the Road Weather Information System (RWIS) site near Byron with new pavement sensors and processing unit
The team looked at the three other intersections between Kasson and Byron. This project will not make changes at those intersections. We will take another look with a future project.
Hwy 14 and Co. Rd. 9 intersection
The Hwy 14 and Co. Rd. 9 intersection hapreferred option is to build a J-turn at the Hwy 14 and Co. Rd. 9 intersection.
s a high risk for severe crashes due to the multi-lane crossing and high traffic speeds. There have been 18 crashes in the past ten years. Three of these crashes involved injuries and one resulted in a fatality. The project team evaluated several options and collaborated with stakeholders and the community. The community also reviewed the options and provided feedback at several public meetings. TheLearn more about J-turns and how they reduce risks for severe crashes.
Construction and Staging Information
You can find detailed information about construction, staging and detour routes in the information tab.
Be sure to sign up for project email updates. This list will be used to provide construction updates.
Please go to the construction website to see the most up-to-date information about the schedule, detour details, etc. This website was used during the public engagement and design phase of the Hwy 14 project. That phase is complete, so now information about the project is on the construction website.
About the project
We will make improvements on Hwy 14 from east of Hwy 56 in Dodge Center to west of Co. Rd. 5 / 2nd Ave. in Byron. Construction will take place spring 2024 and end late summer 2024. The project includes the following improvements:
- Construct a J-turn (also known as a Reduced Conflict Intersection) at Hwy 14 and Co. Rd. 9
- Install a high-tension cable median barrier between Dodge Center and Kasson
- Resurface pavement between Kasson and Byron
- Improve and repair drainage
- Rehabilitate the eastbound and westbound Hwy 14 bridges over Hwy 57. The work includes new end posts, approach panels and expansion joints
- Upgrade the Road Weather Information System (RWIS) site near Byron with new pavement sensors and processing unit
The team looked at the three other intersections between Kasson and Byron. This project will not make changes at those intersections. We will take another look with a future project.
Hwy 14 and Co. Rd. 9 intersection
The Hwy 14 and Co. Rd. 9 intersection hapreferred option is to build a J-turn at the Hwy 14 and Co. Rd. 9 intersection.
s a high risk for severe crashes due to the multi-lane crossing and high traffic speeds. There have been 18 crashes in the past ten years. Three of these crashes involved injuries and one resulted in a fatality. The project team evaluated several options and collaborated with stakeholders and the community. The community also reviewed the options and provided feedback at several public meetings. TheLearn more about J-turns and how they reduce risks for severe crashes.
Construction and Staging Information
You can find detailed information about construction, staging and detour routes in the information tab.
Be sure to sign up for project email updates. This list will be used to provide construction updates.
Provide feedback or ask questions about this project
If you have any questions or comments, please submit them below and we will do our best to get back to you within 3 business days.
MnDOT may share your comments and questions on this site. If you would prefer for your post to remain private, please indicate that along with your message below.
If you have any questions or comments, please submit them below and we will do our best to get back to you within 3 business days.
MnDOT may share your comments and questions on this site. If you would prefer for your post to remain private, please indicate that along with your message below.
-
Share Hwy 14, Dodge Center to Byron. Why is it necessary to be one lane both directions especially the sections with no construction or resurfacing? I drive it every morning and night and it’s been a nightmare this summer! on Facebook Share Hwy 14, Dodge Center to Byron. Why is it necessary to be one lane both directions especially the sections with no construction or resurfacing? I drive it every morning and night and it’s been a nightmare this summer! on Twitter Share Hwy 14, Dodge Center to Byron. Why is it necessary to be one lane both directions especially the sections with no construction or resurfacing? I drive it every morning and night and it’s been a nightmare this summer! on Linkedin Email Hwy 14, Dodge Center to Byron. Why is it necessary to be one lane both directions especially the sections with no construction or resurfacing? I drive it every morning and night and it’s been a nightmare this summer! link
Hwy 14, Dodge Center to Byron. Why is it necessary to be one lane both directions especially the sections with no construction or resurfacing? I drive it every morning and night and it’s been a nightmare this summer!
s.spatenka@yahoo.com asked 4 months agoThanks for contacting us. We know construction slow things down and can frustrate drivers. We appreciate the opportunity to provide some more information.
The single lane closure is for a variety of work: cable median barrier, shoulder work, paving, etc. This week, the crews are working on the final stages of the project - rumble strips, striping, and signing.
We often get questions about lane closures. One of the most common ones has to do with the perception that no workers mean the lane should be open. Unfortunately, it is more complex. Because of this, each project is evaluated to balance the needs of the contractor and the traveling public. Considerations range from safety for all, to current construction work, the space needed for the next day, time spent by the contractor restaging the closure, etc.
This project is in its final stages. Weather permitting, the road should be fully open by mid-August. There may be some short-term single lane closures after as crews finish minor work.
Thank you for your patience and the opportunity to provide some details. Please let us know if you have any additional questions.
-
Share Could you please open up 210th avenue south from 14 going east to avoid gravel!? I have a business and this would generate revenue and easier access for customers from my address 63873 210th Ave dodge center on Facebook Share Could you please open up 210th avenue south from 14 going east to avoid gravel!? I have a business and this would generate revenue and easier access for customers from my address 63873 210th Ave dodge center on Twitter Share Could you please open up 210th avenue south from 14 going east to avoid gravel!? I have a business and this would generate revenue and easier access for customers from my address 63873 210th Ave dodge center on Linkedin Email Could you please open up 210th avenue south from 14 going east to avoid gravel!? I have a business and this would generate revenue and easier access for customers from my address 63873 210th Ave dodge center link
Could you please open up 210th avenue south from 14 going east to avoid gravel!? I have a business and this would generate revenue and easier access for customers from my address 63873 210th Ave dodge center
Joni asked over 1 year agoThank you for your question. We are unable to open 210th Avenue to Highway 14. We manage access to Highway 14 and other highways to reduce conflicts, minimize crashes, reduce delay, and preserve mobility. We accomplish this through the types of access and access spacing. The improvements at Highway 14 and County Road 9 will maintain access at that location and there is full access to the west at Airport Drive. Please reach out to the contacts listed on the site if you have any additional questions.
-
Share Why is one of the original plans not being considered that had a NO at grade crossing? This plan took County 9 west two miles on County 10 to Airport Road, then north to County 34 (Old 14) 1.5 miles, then east 1 mile to County 9 north. This route does not require an overpass now or in the future. This plan was dropped when it was pointed out the Wisconsin engineering company omitted one mile of roadway when designing highway 14 between Kasson and Dodge Center as money was not available. on Facebook Share Why is one of the original plans not being considered that had a NO at grade crossing? This plan took County 9 west two miles on County 10 to Airport Road, then north to County 34 (Old 14) 1.5 miles, then east 1 mile to County 9 north. This route does not require an overpass now or in the future. This plan was dropped when it was pointed out the Wisconsin engineering company omitted one mile of roadway when designing highway 14 between Kasson and Dodge Center as money was not available. on Twitter Share Why is one of the original plans not being considered that had a NO at grade crossing? This plan took County 9 west two miles on County 10 to Airport Road, then north to County 34 (Old 14) 1.5 miles, then east 1 mile to County 9 north. This route does not require an overpass now or in the future. This plan was dropped when it was pointed out the Wisconsin engineering company omitted one mile of roadway when designing highway 14 between Kasson and Dodge Center as money was not available. on Linkedin Email Why is one of the original plans not being considered that had a NO at grade crossing? This plan took County 9 west two miles on County 10 to Airport Road, then north to County 34 (Old 14) 1.5 miles, then east 1 mile to County 9 north. This route does not require an overpass now or in the future. This plan was dropped when it was pointed out the Wisconsin engineering company omitted one mile of roadway when designing highway 14 between Kasson and Dodge Center as money was not available. link
Why is one of the original plans not being considered that had a NO at grade crossing? This plan took County 9 west two miles on County 10 to Airport Road, then north to County 34 (Old 14) 1.5 miles, then east 1 mile to County 9 north. This route does not require an overpass now or in the future. This plan was dropped when it was pointed out the Wisconsin engineering company omitted one mile of roadway when designing highway 14 between Kasson and Dodge Center as money was not available.
Rick asked about 2 years agoHi, that is a good question. The current project is looking at improving safety at the existing Highway 14 and County Road 9 intersection within a limited budget while balancing local property owner access needs with safety and mobility. Closing access at the existing County Road 9 and moving it to another location is beyond the scope of this project and would likely require additional studies to determine the impacts on local property owners, businesses, and long-range county/city/township planning.
-
Share Why is this intersection being done before county road 3? on Facebook Share Why is this intersection being done before county road 3? on Twitter Share Why is this intersection being done before county road 3? on Linkedin Email Why is this intersection being done before county road 3? link
Why is this intersection being done before county road 3?
Shannah B asked about 2 years agoThank you for your question Shannah.
MnDOT initially planned to construct a reduced conflict intersection (RCI) at Olmsted County Road 3 and Olmsted County Road 44 this summer, however the project did not receive approval from ROCOG. We are currently planning to construct the RCI at Olmsted County Road 3 during the summer of 2023.
At this point, we are moving toward the construction of an RCI at Dodge County Road 9 during the summer of 2024.
#countyroad3,#rci#countyroad3 #rci -
Share Save the money and build the overpass and forget anymore stop lights. Don't waste the taxpayers money on this joke of a fix on Facebook Share Save the money and build the overpass and forget anymore stop lights. Don't waste the taxpayers money on this joke of a fix on Twitter Share Save the money and build the overpass and forget anymore stop lights. Don't waste the taxpayers money on this joke of a fix on Linkedin Email Save the money and build the overpass and forget anymore stop lights. Don't waste the taxpayers money on this joke of a fix link
Save the money and build the overpass and forget anymore stop lights. Don't waste the taxpayers money on this joke of a fix
Crazy Larry asked over 2 years agoStop lights won't be installed at County Road 9 or 260 Avenue. Crash analyses show an increased crash rate with stop lights on high-speed rural highways at low-volume intersections.
We are constrained by fiscal budgets and responsibly spend taxpayer dollars. You noted taxpayers’ money is important to you, and we recommend you give a second look at the proposed RCI. Bridges cost millions of dollars. However, an RCI about $1 million to construct and effectively reduces severe and deadly crashes. You can learn more about RCIs on MnDOT's website here: http://www.dot.state.mn.us/roadwork/rci/.
-
Share Why is there not a plan for acceleration lanes at CR 15? on Facebook Share Why is there not a plan for acceleration lanes at CR 15? on Twitter Share Why is there not a plan for acceleration lanes at CR 15? on Linkedin Email Why is there not a plan for acceleration lanes at CR 15? link
Why is there not a plan for acceleration lanes at CR 15?
gaersland asked over 2 years agoAcceleration lanes are useful when high volumes of trucks enter the highway at a single point (e.g., at an ethanol plant). They reduce the time a trucker needs to wait for a gap in the traffic by giving them a protected space to accelerate. Analysis shows they do not reduce serious crashes, and the limited studies suggest that they increase the number of minor crashes.
acceleration lanesacceleration lanes -
Share Why not close both intersections and move the traffic to the interchanges in Kasson and Dodge Center and CR 15? on Facebook Share Why not close both intersections and move the traffic to the interchanges in Kasson and Dodge Center and CR 15? on Twitter Share Why not close both intersections and move the traffic to the interchanges in Kasson and Dodge Center and CR 15? on Linkedin Email Why not close both intersections and move the traffic to the interchanges in Kasson and Dodge Center and CR 15? link
Why not close both intersections and move the traffic to the interchanges in Kasson and Dodge Center and CR 15?
gaersland asked over 2 years agoClosing the intersections is an option we consider when evaluating intersection safety improvements. But closing intersections also makes it harder for local property owners to do business, farm, and get to and from their homes. We are looking for ways to balance safety improvements with local property access.
-
Share How are tractors and wagons supose to get across the hwy. It's going to be a suicide trip to get across the road on Facebook Share How are tractors and wagons supose to get across the hwy. It's going to be a suicide trip to get across the road on Twitter Share How are tractors and wagons supose to get across the hwy. It's going to be a suicide trip to get across the road on Linkedin Email How are tractors and wagons supose to get across the hwy. It's going to be a suicide trip to get across the road link
How are tractors and wagons supose to get across the hwy. It's going to be a suicide trip to get across the road
Crazy Larry asked over 2 years agoCrossing a four-lane divided highway can be dangerous. We are planning a reduced conflict intersection (RCI) at Highway 14 and County Road 9. RCIs are proven to reduce the number and severity of crashes – especially right-angle crashes. The plan includes widened shoulders to give extra space for agricultural equipment to cross without having to enter Highway 14 traffic. You can learn more about RCIs on MnDOT's website here: http://www.dot.state.mn.us/roadwork/rci/.
-
Share Will the be adding acceleration lanes on the highway where the cross intersections will be closed? If not, I hope they reconsider as this greatly reduces near incidents. on Facebook Share Will the be adding acceleration lanes on the highway where the cross intersections will be closed? If not, I hope they reconsider as this greatly reduces near incidents. on Twitter Share Will the be adding acceleration lanes on the highway where the cross intersections will be closed? If not, I hope they reconsider as this greatly reduces near incidents. on Linkedin Email Will the be adding acceleration lanes on the highway where the cross intersections will be closed? If not, I hope they reconsider as this greatly reduces near incidents. link
Will the be adding acceleration lanes on the highway where the cross intersections will be closed? If not, I hope they reconsider as this greatly reduces near incidents.
Jess asked over 2 years agoAcceleration lanes are useful when high volumes of trucks are entering the highway at a single point (e.g., at an ethanol plant). They reduce the time a trucker needs to wait for a gap in the traffic by giving them a protected space to accelerate. Analysis shows they do not reduce serious crashes, and the limited studies suggest that they increase the number of minor crashes.
acceleration lanesacceleration lanes
Sign up for email updates
Schedule
-
May-July 2022
Hwy 14 and Co. Rd. 9 — J-turn has finished this stageIdentify issues and needs of the community
-
August-September 2022
Hwy 14 and Co. Rd. 9 — J-turn has finished this stageDesign concepts and evaluate with the community
-
Winter 2022/23
Hwy 14 and Co. Rd. 9 — J-turn has finished this stageSelect the preferred option, share and educate the community
-
Winter-Fall 2023
Hwy 14 and Co. Rd. 9 — J-turn has finished this stagePrepare final documents for construction contract
-
Spring-Summer 2024
Hwy 14 and Co. Rd. 9 — J-turn is currently at this stageConstruction
Contacts
-
Email tom.austin@state.mn.us -
Phone 507-951-6593 Email cindy.morgan@state.mn.us
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends