Construction Staging
Construction Stage 1
Construction will occur in two stages; inside lanes and outside lanes. The contractor will determine which stage will occur first. However, the bridge improvements at Hwy 57 will start with the inside lanes. Once construction begins, vehicles will not be able to cross or turn left onto Hwy 14 from Co. Rd. 9. One lane of traffic in each direction on Hwy 14 will be open throughout construction.
Stage one construction will include:
- Median U-turns and left turn lanes at Co. Rd. 9*
- High-tension cable median barrier installation*
- Bridge approach panels
- Overlay
*When these items are complete, stage 2 will begin, even if stage 1 bridge and overlay work is still being done. This will minimize the need for the Co. Rd. 9 detour.
Construction Stage 2
Construction will occur in two stages; inside lanes and outside lanes.
The contractor will determine which stage will occur first. However, the bridge improvements at Highway 57 will start with the inside lanes. Once construction begins, vehicles will not be able to cross or turn left onto Highway 14 from County Road 9. One lane of traffic in each direction on Highway 14 will be open throughout construction. When construction is complete, vehicles will be able to use the J-turn to access Highway 14 and County Road 9.
Stage two construction will include:
- Right turn lane extensions and “porkchops” at County Road 9
- Bridge approach panels
- Overlay
Detour Route
What to expect
Vehicles to the north of Hwy 14 will be detoured west on Co. Rd. 34 to southbound 200th Ave./Airport Dr. N to Hwy 14. Vehicles to the south of Hwy 14 will be detoured west on Co. Rd. 10 to Co. Rd. 25/Airport Dr. S to Hwy 14.