March → May 2026

Phase 1: Project introduction, Gather information

In this phase, we will introduce the project and gather input on existing issues and opportunities.

June → August 2026

Phase 2: Shape concepts

The second phase will share how community input shaped project alternatives and ask for feedback on prioritizing designs.

September → November 2026

Phase 3: Inform and Wrap Up

The last phase of engagement will share the final road design recommendation.

May 01 → August 31 2030

Construction

Construction tentatively planned for Summer 2030

December 01 2026 → April 30 2030

Project devekopment

Additional phases and timelines will be added as the project progresses.