Develop project
MnDOT will reconstruct the Hwy 24 interchange at I-94 between 179th St. to Ash St. in Clearwater.
Final design and work staging will continue through 2025, with construction expected to begin in summer 2026 and wrap up by late fall 2027.
Larger area evaluated
Although current funding only allows us to reconstruct the Hwy 24 interchange at I-94, MnDOT has evaluated the entire one-mile stretch of Hwy 24 through Clearwater,from Co. Rd. 7 to the Mississippi River.
Current and future safety and mobility needs
Pedestrian and bicycle resources
Access needs
Long-term vision for this area of Hwy 24
Analysis will result in a selected preliminary design
This will support future funding opportunities, allow the community to plan ongoing development, and minimize rework when the rest of the area is reconstructed in the future.
Public meeting Mon, Sept. 29
Join the project team to learn about future 2026-2027 construction staging, impacts and schedule:
4-6 p.m. Lions Park Pavilion 1100 County Road 75, Clearwater
There’s no formal presentation—just stop by anytime to view project displays, ask questions and talk with the project team.
MnDOT will reconstruct the Hwy 24 interchange at I-94 between 179th St. to Ash St. in Clearwater.
Final design and work staging will continue through 2025, with construction expected to begin in summer 2026 and wrap up by late fall 2027.
Larger area evaluated
Although current funding only allows us to reconstruct the Hwy 24 interchange at I-94, MnDOT has evaluated the entire one-mile stretch of Hwy 24 through Clearwater,from Co. Rd. 7 to the Mississippi River.
Current and future safety and mobility needs
Pedestrian and bicycle resources
Access needs
Long-term vision for this area of Hwy 24
Analysis will result in a selected preliminary design
This will support future funding opportunities, allow the community to plan ongoing development, and minimize rework when the rest of the area is reconstructed in the future.
Public meeting Mon, Sept. 29
Join the project team to learn about future 2026-2027 construction staging, impacts and schedule:
4-6 p.m. Lions Park Pavilion 1100 County Road 75, Clearwater
There’s no formal presentation—just stop by anytime to view project displays, ask questions and talk with the project team.
Share Clearwater community invited to public meeting to learn future work and traffic plans on FacebookShare Clearwater community invited to public meeting to learn future work and traffic plans on TwitterShare Clearwater community invited to public meeting to learn future work and traffic plans on LinkedinEmail Clearwater community invited to public meeting to learn future work and traffic plans link
Construction is coming on Hwy 24 in Clearwater! Come learn about the plan, travel impacts and schedule at our public meeting:
Mon, Sept. 29
4 to 6 p.m. Lions Park Pavilion 1100 Co. Rd. 75 Clearwater
There’s no formal presentation—just stop by anytime to view project displays, ask questions and talk with the project team.
This project is in partnership with the City of Clearwater and Wright County and will improve safety, traffic flow and access through Clearwater. Final design work will continue through 2025, with construction expected to begin in summer 2026 and wrap up by late fall 2027.
Hwy 24 Clearwater project improvements map
Hwy 24 improvements
MnDOT will reconstruct the Hwy 24 bridge over I-94 between 179th St. and Ash St. in Clearwater, Wright County, in 2026-2027.
Build a new Hwy 24 bridge over I-94, southeast of the current bridge
Reconstruct Hwy 24 from Wright Co. Rd. 145 (179th St.) to Smith St.
Improve access and traffic flow with:
Two roundabouts at the I-94 westbound and eastbound ramps
A teardrop-style roundabout at Hwy 24 and Wright Co. Rd. 145
New road approaches at Ash St. and Nelson Dr.
Extend the multi-use trail and sidewalks between Co. Rd. 145 and Co. Rd. 75
Connect with Wright County’s roundabout project at Hwy 24 and Co. Rd. 7
Share City of Clearwater approves proposed layout for Hwy 24 on FacebookShare City of Clearwater approves proposed layout for Hwy 24 on TwitterShare City of Clearwater approves proposed layout for Hwy 24 on LinkedinEmail City of Clearwater approves proposed layout for Hwy 24 link
The Clearwater City Council held a public hearing on Oct. 14 and approved the proposed Hwy 24 interchange project layout.
• MnDOT is in the design phase for the interchange project at Hwy 24 and Interstate 94.
• The city council also approved the roundabout project at Hwy 24 and Co. Rd. 7. The city, MnDOT and Wright County are seeking funding to construct the roundabout.
• The city did not approve the proposed roundabout at Hwy 24 and Co. Rd. 75. Discussions will continue to determine the next steps for this part of the project.
Share Learn more about the selected design on FacebookShare Learn more about the selected design on TwitterShare Learn more about the selected design on LinkedinEmail Learn more about the selected design link
Thank you all for attending the Hwy 24 – Clearwater public meeting on Tue, Oct. 1. We received valuable feedback from many community members and businesses.
Check out the below materials if you were unable to make it to our public meeting:
Share Past Events on FacebookShare Past Events on TwitterShare Past Events on LinkedinEmail Past Events link
Public meeting: Oct. 1, 2024
A public meeting was held on Tue, Oct. 1 from 4 - 6 p.m. at Lions Park Pavilion (1100 County Road 75, Clearwater) to learn more about the selected design and next steps for the Hwy 24 corridor.
Check out the below video that discusses the project area and the design alternatives currently being considered.
May and June Public Meetings
Thank you for your interest in the Hwy 24 Clearwater project. A public open house was held on Thursday, May 9, at Lion's Park Pavilion in Clearwater. Previous business meetings were held on May 9 and June 4.
If you were unable to attend or would like to review the open house materials again, please contact us.
Page last updated: 25 Sep 2025, 11:18 AM
Sign up for email updates
Schedule
February 2024 – May 2024: Introduce, develop and recommend design concept
Hwy 24 — Clearwater has finished this stage
Introduce project, learn more about the current conditions and issues
Develop design concepts and recommend final design concept
May 2024 – October 2024: Refine recommended design and develop project layout
Hwy 24 — Clearwater has finished this stage
Continue to develop recommended design concept
Present final design to community and collect feedback on final design layout
November 2024 –2026: Input on final design and construction staging