May 2024 public meeting materials
Community members shared their experiences on Highway 52 over the past year.\
The project team has finished analyzing the potential concepts and will share which concepts are recommended for future consideration.
Share feedback on the recommendations on the Study Recommendations Survey.
Note: The concepts were called alternatives in previous phases.
Recommendation
Carried forward
No Build:
The No Build concept represents a maintenance only approach. It is used to evaluate potential improvements that a concept would provide.
Concept 4:
- Full access interchange at 165th Ave.
- Access closures and new frontage roads
- New frontage road along southbound Hwy 52 with new river bridge
- 165th Ave. would become Co. Rd. 7 from Hwy 52 north to 400th St. then west to existing Co. Rd. 7
- Existing Co. Rd. 7 would turn back to township
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 4: Overpass at new CR 7 & Interchange at 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Good |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Fair |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Good |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Good |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Note: Concept figures are preliminary and subject to change. Concept figures represent one potential option of many that could be implemented in the future. No detailed design or analysis has been completed at this stage.
Concept 5:
Full access interchange at Co. Rd. 7
- Right-in/right-out at 165th Ave.
- Access closures and new frontage roads
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 5: J-Turns at CR 7 and 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Good |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Good |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Good |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Good |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Note: Concept figures are preliminary and subject to change. Concept figures represent one potential option of many that could be implemented in the future. No detailed design or analysis has been completed at this stage.
Concept 7:
Full access interchange at 165th Ave.
- Overpass to north of Co. Rd. 7
- New Co. Rd. 7 from north of 420th St. to Hwy 52
- New township road from Hwy 52 to Sherwood Trl.
- Access closures and new frontage roads
- Existing Co. Rd. 7 turn back to township
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 7: Interchange at CR 7 |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Good |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Good |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Good |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Good |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Note: Concept figures are preliminary and subject to change. Concept figures represent one potential option of many that could be implemented in the future. No detailed design or analysis has been completed at this stage.
Local road:
Various improvements to area local roads.
Local Roads Potential Projects
Project |
Segment/Improvement |
Planning-level cost |
Project Timeline |
A |
Closure of driveways 1 & 2 and associated frontage road |
$1,493,200 |
Short-term |
B |
Closure of driveway 3 and associated frontage road |
$455,600 |
Short-term |
C |
Closure of driveways 5, 7 & 9, plus associated frontage road lay that exceeds Level of Service E |
$2,410,300 |
Short-term |
D |
Closure of driveways 4, 6 & 8, plus associated frontage road feasible accommodations |
$1,301,100 |
Short-term |
E |
Closure of driveways 13 & 14, plus associated frontage road |
$781,200 |
Short-term |
F |
445th Street (access point 15) closure |
$20,000 |
Short-term |
G |
445th Street Overpass (over US 52) |
$14,780,000 |
Long-term |
H |
145th Ave Extension (over the North Fork Zumbro River) |
$4,118,000 |
Long-term |
I |
440th St Extension (over the North Fork Zumbro River) |
$19,100,600 |
Long-term |
Eliminated
Concept 1:
- J-turn at Co. Rd. 7
- J-turn at 165th Ave.
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 1: J-Turns at CR 7 and 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Fair |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Fair |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Poor |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Fair |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Concept 2:
- J-turn at 165th Ave.
- J-turn at Co. Rd. 7
- 165th Ave. would become Co. Rd. 7 from Hwy 52 north to 400th St. then west to existing Co. Rd. 7
- Existing Co. Rd. 7 would turn back to township
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 2: High T at CR 7 and 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Fair |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Poor |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Poor |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Fair |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Concept 3:
- High-T intersection at Co. Rd. 7
- High-T intersection at 165th Ave.
- Access closures and new frontage roads
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 3: Interchange at CR 7 |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Fair |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Fair |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Good |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Good |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Concept 6:
- Full access interchange to north of existing Co. Rd. 7
- New Co. Rd. 7 from north of 420th St. to Hwy 52 new full access interchange
- New township road south of interchange to Sherwood Trl.
- J-turn at 165th Ave.
- Access closures and new frontage roads
- Existing Co. Rd. 7 turn back to township
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 6: High T at CR 7 and 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Fair |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Fair |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Fair |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Good |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Not Recommended
Note: Not recommended at this time. A review in the future may be warranted.
Concept 8:
- J-turn at 165th Ave.
- Overpass to north of Co. Rd. 7
- New Co. Rd. 7 from north of 420th St. to Hwy 52
- New township road from Hwy 52 to Sherwood Trl.
- Access closures and new frontage roads
- Existing Co. Rd. 7 turn back to township
Primary Needs Evaluation
Evaluation Approach |
Evaluation Results |
Evaluation Scoring |
|||||
Criteria |
Performance Measure |
No Build: Baseline - maintain existing condition |
Concept 8: Overpass at new CR 7 & Interchange at 165th |
Poor = |
Fair = |
Good = |
|
Vehicle Safety |
Corridor/ network and intersection crashes |
Expected crashes & Expected Severe Crashes (Crash Modification Factors) |
Poor |
Good |
No anticipated crash reduction |
Anticipated crash reduction of 0 to 50% |
Anticipated crash reduction of greater than 50% |
Vehicle Mobility |
Connectivity - Crossing US 52 on the local road network |
Travel time to cross US 52 |
Fair |
Good |
Travel times vs. No Build: Significant increase |
Travel times vs. No Build: Similar or slight increase (5% reduction to a 15% increase) |
Travel times vs. No Build: Reduced |
Gap Acceptance |
Side-street delay for all turning vehicles |
Poor |
Fair |
Intersections that have side-street delay that exceeds Level of Service E: 25% or More |
Intersections that have side-street delay that exceeds Level of Service E: Less than 25% |
Intersections that have side-street delay that exceeds Level of Service E: None |
|
Geometric limitations for slow-moving large vehicles on US 52 |
Ability to accommodate slow-moving and large vehicles and divert them to local road/off of US 52 (i.e., agricultural equipment, school buses, and freight/semi-trucks) |
Poor |
Fair |
Feasible accommodations provided by concept: None |
Feasible accommodations provided by concept: Some |
Feasible accommodations provided by concept: A majority |
Next steps
MnDOT will work with agency partners to identify and secure funding for future steps. Once funding is secured, then the additional steps of selecting and refining a design would occur. Construction would be the final step. All this could take an additional 5-7 years after funding is secured.
Evaluation results
The team used input from the community and technical knowledge to evaluate each concept. A sample of results are with each Concept above. Additional evaluation criteria and results are in the Concept Analysis memo, starting on page 41, in the Important Documents section.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends