Option 2- Partial closures
Proposes staged lane closures between Hwy 71 and Hannah Ave. This option prioritizes keeping traffic driving through the construction zone with a lane of traffic open through the project. The downside is that it takes much longer to construct and requires a more complex staging plan. This option would push construction into a second year (2026 & 2027).
*both options have Gillette Dr to Hwy 71 constructed half at a time (i.e. single lane traffic through the construction zone)
Answer the Survey to let us know which you prefer.