Highway 16 reconstruction and bridge replacement in Houston

Share Highway 16 reconstruction and bridge replacement in Houston on Facebook Share Highway 16 reconstruction and bridge replacement in Houston on X (formerly Twitter) Share Highway 16 reconstruction and bridge replacement in Houston on Linkedin Email Highway 16 reconstruction and bridge replacement in Houston link

Thank you for joining us on Sept. 9 for a public meeting.

Thank you to the nearly 40 people who turned out for our public meeting on Sept. 9 to share your experiences, observations and concerns about this stretch of highway.

If you need an ASL, or a foreign language interpreter, or documents in an alternative format please contact Janet Miller at 651-366-4720 (711 or 1-800-627-3529 for MN Relay). If you need any other reasonable accommodation to participate, please email your request to ADArequest.dot@state.mn.us.

Unable to attend?

That's OK if you were unable to attend the meeting. We've included the information boards that were at the meeting.

Look through and let us know your thoughts, concerns, ideas. This is an important time to include your ideas or locations and features that you feel need emphasis for improvements. You can find the boards on our link.

How to comment?

Send us an email. You can click on our contacts on this page and send your thoughts to us: what works well? What needs improvement? Are there safety concerns and what would you recommend? Are there any key community events or activities to consider once we start developing the construction plan? (Think like Houston Hoedown Days or harvest and planting seasons.)



We are planning improvements on Highway 16 in Houston.

Construction is expected to begin in 2031 with the following proposed improvements:

  • Reconstruct Highway 16
  • Improve drainage
  • Replace city sewer and water utilities
  • Replace bridge east of Houston (Bridge 95111)
  • Improve bike and pedestrian sidewalks, crossings and overall safety

This project follows MnDOT’s Complete Streets and Safe System approaches. The new design will better serve people walking, biking, driving and using mobility devices while improving overall safety.

Project map showing repaving areas and reconstruction areas plus bridge replacement location.

Project timeline

  • Data collection and scoping: Summer 2026 to winter 2027
  • Preliminary design: Spring 2027 to spring 2029
  • Final design: Summer 2029 to fall 2030
  • Project letting: Oct. 23, 2030

We are planning to hold more public meetings: Winter 2027, summer 2027, spring/summer 2028 and fall/winter 2029.

Project time grid showing phase 1, 2, 3 with icons of people and drawings.


Thank you for joining us on Sept. 9 for a public meeting.

Thank you to the nearly 40 people who turned out for our public meeting on Sept. 9 to share your experiences, observations and concerns about this stretch of highway.

If you need an ASL, or a foreign language interpreter, or documents in an alternative format please contact Janet Miller at 651-366-4720 (711 or 1-800-627-3529 for MN Relay). If you need any other reasonable accommodation to participate, please email your request to ADArequest.dot@state.mn.us.

Unable to attend?

That's OK if you were unable to attend the meeting. We've included the information boards that were at the meeting.

Look through and let us know your thoughts, concerns, ideas. This is an important time to include your ideas or locations and features that you feel need emphasis for improvements. You can find the boards on our link.

How to comment?

Send us an email. You can click on our contacts on this page and send your thoughts to us: what works well? What needs improvement? Are there safety concerns and what would you recommend? Are there any key community events or activities to consider once we start developing the construction plan? (Think like Houston Hoedown Days or harvest and planting seasons.)



We are planning improvements on Highway 16 in Houston.

Construction is expected to begin in 2031 with the following proposed improvements:

  • Reconstruct Highway 16
  • Improve drainage
  • Replace city sewer and water utilities
  • Replace bridge east of Houston (Bridge 95111)
  • Improve bike and pedestrian sidewalks, crossings and overall safety

This project follows MnDOT’s Complete Streets and Safe System approaches. The new design will better serve people walking, biking, driving and using mobility devices while improving overall safety.

Project map showing repaving areas and reconstruction areas plus bridge replacement location.

Project timeline

  • Data collection and scoping: Summer 2026 to winter 2027
  • Preliminary design: Spring 2027 to spring 2029
  • Final design: Summer 2029 to fall 2030
  • Project letting: Oct. 23, 2030

We are planning to hold more public meetings: Winter 2027, summer 2027, spring/summer 2028 and fall/winter 2029.

Project time grid showing phase 1, 2, 3 with icons of people and drawings.