Highway 16 reconstruction and bridge replacement in Houston
Share Highway 16 reconstruction and bridge replacement in Houston on FacebookShare Highway 16 reconstruction and bridge replacement in Houston on X (formerly Twitter)Share Highway 16 reconstruction and bridge replacement in Houston on LinkedinEmail Highway 16 reconstruction and bridge replacement in Houston link
Thank you for joining us on Sept. 9 for a public meeting.
Thank you to the nearly 40 people who turned out for our public meeting on Sept. 9 to share your experiences, observations and concerns about this stretch of highway.
If you need an ASL, or a foreign language interpreter, or documents in an alternative format please contact Janet Miller at 651-366-4720 (711 or 1-800-627-3529 for MN Relay). If you need any other reasonable accommodation to participate, please email your request to ADArequest.dot@state.mn.us.
Unable to attend?
That's OK if you were unable to attend the meeting. We've included the information boards that were at the meeting.
Look through and let us know your thoughts, concerns, ideas. This is an important time to include your ideas or locations and features that you feel need emphasis for improvements. You can find the boards on our link.
How to comment?
Send us an email. You can click on our contacts on this page and send your thoughts to us: what works well? What needs improvement? Are there safety concerns and what would you recommend? Are there any key community events or activities to consider once we start developing the construction plan? (Think like Houston Hoedown Days or harvest and planting seasons.)
We are planning improvements on Highway 16 in Houston.
Construction is expected to begin in 2031 with the following proposed improvements:
Reconstruct Highway 16
Improve drainage
Replace city sewer and water utilities
Replace bridge east of Houston (Bridge 95111)
Improve bike and pedestrian sidewalks, crossings and overall safety
This project follows MnDOT’s Complete Streets and Safe System approaches. The new design will better serve people walking, biking, driving and using mobility devices while improving overall safety.
Project timeline
Data collection and scoping: Summer 2026 to winter 2027
Preliminary design: Spring 2027 to spring 2029
Final design: Summer 2029 to fall 2030
Project letting: Oct. 23, 2030
We are planning to hold more public meetings: Winter 2027, summer 2027, spring/summer 2028 and fall/winter 2029.
Thank you for joining us on Sept. 9 for a public meeting.
Thank you to the nearly 40 people who turned out for our public meeting on Sept. 9 to share your experiences, observations and concerns about this stretch of highway.
If you need an ASL, or a foreign language interpreter, or documents in an alternative format please contact Janet Miller at 651-366-4720 (711 or 1-800-627-3529 for MN Relay). If you need any other reasonable accommodation to participate, please email your request to ADArequest.dot@state.mn.us.
Unable to attend?
That's OK if you were unable to attend the meeting. We've included the information boards that were at the meeting.
Look through and let us know your thoughts, concerns, ideas. This is an important time to include your ideas or locations and features that you feel need emphasis for improvements. You can find the boards on our link.
How to comment?
Send us an email. You can click on our contacts on this page and send your thoughts to us: what works well? What needs improvement? Are there safety concerns and what would you recommend? Are there any key community events or activities to consider once we start developing the construction plan? (Think like Houston Hoedown Days or harvest and planting seasons.)
We are planning improvements on Highway 16 in Houston.
Construction is expected to begin in 2031 with the following proposed improvements:
Reconstruct Highway 16
Improve drainage
Replace city sewer and water utilities
Replace bridge east of Houston (Bridge 95111)
Improve bike and pedestrian sidewalks, crossings and overall safety
This project follows MnDOT’s Complete Streets and Safe System approaches. The new design will better serve people walking, biking, driving and using mobility devices while improving overall safety.
Project timeline
Data collection and scoping: Summer 2026 to winter 2027
Preliminary design: Spring 2027 to spring 2029
Final design: Summer 2029 to fall 2030
Project letting: Oct. 23, 2030
We are planning to hold more public meetings: Winter 2027, summer 2027, spring/summer 2028 and fall/winter 2029.